PMP Exam Simulator
3h 50m 0s
Risk Management
You started a new project which is very important for the company. Due to the critical nature of the project you realize how important it is to perform thorough risk management. You have to be sure that you have considered all relevant project information before beginning. Which of the following is not always an input to the risk management process?