Risk Management
One of the following risk events is most likely to interfere with attaining a project's schedule objective. Which risk event is it?
Substantial increases in the cost of purchased materials.
Contract disputes that generate claims for increased payments.
Delays in obtaining required approvals.
Slippage of the planned post-implementation review meeting.