info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

The project you are managing is to decrease the negative impact that construction landfills pose on the environment. The next step of your project is to line a new landfill with a membrane that is specially designed to catch methane in liquid form and prevent it from escaping into the air. This is one of the well-established techniques available to reliably and consistently treat landfill wastes. You need special equipment that your vendor is supposed to deliver from another state. Today you were informed that due to severe weather conditions the vendor will not be able to deliver the equipment on time. You respond to the risk by leasing the required equipment from a local company until yours arrives. Your response to the situation is: