PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Risk Management
You are considering purchasing a new piece of equipment for your project that was not available when the project began. The team is trying to determine which risks have the most potential impact on the project. The team is using a diagram to display this sensitivity analysis data by examining all uncertain elements at their baseline values. Which type of diagram is the team using?