The project manager has been assigned to a project to develop a mail delivery service using drones for people who live in remote places. The project has huge perspectives and the service is expected to become widely used. The project manager is now performing a quantitative risk analysis and modeling technique that helps to determine which risks have the most potential impact on the project. He needs to find whether the occurrence of a particular threat would be merely an inconvenience or would ruin the project. The most appropriate tool for the project manager to use in this situation is: