PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

The project manager is in the Develop Team process of the project to develop a mobile application. While referring to Tuckman's model, the project manager notices that the team is in a stage where her role is mostly overseeing and delegating. In which stage of team development is the team right now?