PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Resource Management
You are the project manager of the project to create an application for university students. This project will last for one year and you have 30 project team members. You have been requested by the management to create a chart depicting all the project resource needs and the associated activities. The type of chart that the management expects is: