Today you had a meeting with the team regarding the equipment needed for the project. It has been determined that the team will need a very specialized thermostat for the period of at least three months. The company has one thermostat of that kind, however, it's needed for another project. Buying another thermostat is assumed to be cost-prohibitive. The least effective action for the project manager to take is: