PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Resource Management
You are a project manager and you have been successfully working on the current project. You are on schedule to meet an aggressive deadline when the successor activity to a critical path activity suffers a major setback. There are 5 team members working on the activity. Also, the activity has 15 days of float. If needed, there are other team members who are able to help with this particular activity. In addition to that, one team member wants to leave the project because he doesn't believe in success of the project. After a brief meeting you realise that this team member has some issues that have not been addressed. You definitely want to improve the project, therefore, the best thing for you to do is: