PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Resource Management
There are 10 different departments involved in the project. The project charter has been signed by one person and contains over 20 requirements. The project manager has just been hired. He right away identified 40 stakeholders; the schedule objectives on the project are constrained. What type of power is the most effective to help the project manager gain the cooperation of others?