PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Resource Management
You are managing a project to merge two existing applications into one for an accounting company. You need two additional resources from different functional areas. Today you had a meeting to discuss this issue, however, the functional manager was reluctant to assign her resources to your project. You tried to make the functional manager change her mind by using your association with a high-level executive for leverage. By doing this, you used which one of the following forms of power?