PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Scope Management
Fred is a project manager and he has just had a meeting with the project stakeholders. They asked Fred to add work to the project scope. Before the project charter was signed, Fred had access to correspondence about the project. He remembers clearly that the project sponsor denied funding for the scope mentioned by the stakeholders at the meeting. What is the best thing for Fred to do?