lock iconProject Management Terms

The projet manager has just completed an important project to update the organization's software system. Now, ongoing operations and maintenance are being performed by the support team to make sure all the servers and routers are operating well. A considerable part of your project budget is allocated to maintenance. You will be sending out daily status updates and resolving issues. However, there is no need for planning or providing documentation. These ongoing operations and maintenance are important to the products of your project and should be considered as: