PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Project Management Terms
You are overseeing a project to implement a new video game console. As long as not everything is known upfront, you choose the approach of defining and developing the product by incremental steps and continually reviewing and adjusting processes, requirements and decisions throughout the project life cycle as the project progresses. In which of the following are you engaged?