lock iconProject Management Responsibility

As a contracted project manager, you have been assigned to a project with a budget of $1 million. The project is scheduled to last one year, but your most recent EVM report shows that the project will finish ahead of schedule by nearly four weeks. If this happens, you will lose $75,000 in billable time. What should you do?