lock iconProject Management Responsibility

You are the project manager of the project on hotel construction. Your organization is a functional environment. Unfortunately, you do not get along with the functional manager leading the project. You two are in disagreement about how the project should proceed, the timings of the activities, the suggested schedule and the expected quality of the work. The manager has requested that you get to work on several of the activities on the critical path even though you both have not solved the problems concerning the project. What should you do?