lock iconProject Management Responsibility

You have been assigned to a project that will involve team members from five different countries. On the one hand, the project has strong support from senior management, on the other hand, this type of project is new to everyone on the team. In order to make sure the cultural differences don't interfere with the project, the project manager has to: