Based on your report to the senior management, the project you are currently managing is on schedule and under budget. In order to prepare this report, you performed earned value calculations on the project. Unfortunately, right after the meeting when the report was presented to the management, you found out that the numbers you used in the calculations were wrong. These numbers were taken from the old document which hadn't been updated. Your next step should be: