Project Management Responsibility
Your project to build a software application which would synchronize appointments from different calendars in one application is in progress. This software application will be used by a large corporation and they need it available as soon as possible due to recent growth and overwhelming appointments with customers. While reviewing one of the components, you realize that the component does not meet the quality standards of the corporation. After further investigation, you discover that the component does not necessarily has to meet the specified quality standards and that the component will function as it is totally fine. Besides, the team member responsible for the component made it clear that meeting the specified quality standards will add cost. What should you do in this situation as the project manager?