Project Management Processes
All of the following statements are correct regarding the initiating process group EXCEPT:
Stakeholder influence is highest at the start and diminishes as the project proceeds.
The project manager and project team are always identified as part of the initiating process group.
Project risk is highest at the beginning of the project and reduces as the project approaches the end.
Cost and staffing start low, increase towards the end and drop rapidly near closing.