PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Project Management Processes
Veronika is a team member and during last team meeting she asked about the measurements that will be used on the project to assess performance. She believes some of the measures related to activities assigned to her are not valid. The project is most likely in which part of the project management process?