Project Management Processes
You are managing a new wireless media streaming device development project for a government institution. At the moment you are collecting the requirements of the project. You are worried that the stakeholders might give you incorrect requirements. You set up a meeting with the sponsor and tell him to observe the customers as they work to understand the problem with the current media streaming system. After doing this process, what process should you do next?