PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Project Management Framework
It's been decided by your management team that all orders will be treated as projects and that project managers will be used to update orders daily, resolve issues and make sure that customers formally accept the product within 30 days of completion. Revenue from individual orders can range from $100 to $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?