This app works best with JavaScript enabled.
PRACTICE
Home
Blog
Vocabulary
Sign In
Sign Up
Home
Blog
Vocabulary
Sign In
Sign Up
PMP Exam Simulator
Duration
3h 50m 0s
Questions
Start
Accelerate Mock Exam
Display correct answer
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Procurement Management
The buyer's project manager needs to ensure that the seller is not making extra profits in the Cost Plus Fixed Fee (CPFF) contract. The best way to do it is to:
Only pay the fee when the project is completed.
Ensure that the sellers are not cutting scope.
Not authorize any unexpected cost overrun.
Audit all invoices and make sure that you are not charged for items not chargeable to the project.
Next