PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProcurement Management

During the Control Procurements process, the project manager is meeting with the seller to check on the product itself and its conformance to specification. The project manager is performing: