PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProcurement Management

A contract between your organization and a vendor includes a clause that penalizes the vendor if the project is late. The lateness of a project has a monetary penalty. Thus, the penalty should be enforced or waived based on: