This app works best with JavaScript enabled.
PRACTICE
Home
Blog
Vocabulary
Sign In
Sign Up
Home
Blog
Vocabulary
Sign In
Sign Up
PMP Exam Simulator
Duration
3h 50m 0s
Questions
Start
Accelerate Mock Exam
Display correct answer
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Procurement Management
The WBS and the WBS dictionary can help project managers plan for purchases and acquisitions. Which one of the following best describes this process?
Both parties must have and retain their own copy of the WBS.
The WBS defines the specific contracted work.
The WBS defines the requirements for the specific contracted work.
The WBS defines the specific contracted work, which must support the requirements of the project customer.
Next