Procurement Management
The project manager has completed the SOW describing specifications and other requirements for an expensive compactor for his construction project. He put together some documents to solicit proposals from potential vendors, identified the type of the contract that he wants to use and terms and conditions. What tools and techniques will the project manager use in the next process?