Procurement Management
You are managing a project for a company that specializes in interior and exterior design. The number of projects has increased recently and the company has outsourced a large portion of activities to a vendor. According to the contract, the vendor must consult with the team of architects in your company before submitting any additional design elements to the project. The vendor has already submitted several new elements to the exterior design project you are managing without consulting with the architects in your organization. As a project manager, you should: