lock iconProcurement Management

You are overseeing the development of a color correction and non-linear video editing application. It's designed for multi-user collaboration so that editors, assistants, colorists, artists and sound designers can all work live on the same project at the same time. Recently, a new sound effect technology has been introduced to the sound industry and the management requested that you speak to the vendor regarding the implementation of this new technology as soon as possible. The implementation of this feature will help to avoid losing a significant market share. In your opinion, what should be included in the contract in this scenario?