Risk Management
Outputs of the Plan Risk Responses process include:
Project management plan updates, contingency plans and sensitivity analysis.
Process updates, secondary risks and risk owners.
Contracts, risk triggers and a risk list.
Fallback plans, residual risks and contingency reserves.