PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconProject Management Framework

Your organization used to have the strong matrix structure. Now it's become project oriented. Project team members admit there are many benefits for the team and organization, but also agree there are certain drawbacks of project-oriented organizations comparing to strong matrix organizations. That's because in a project-oriented organization, the project team: