This app works best with JavaScript enabled.
PRACTICE
Home
Blog
Vocabulary
Sign In
Sign Up
Home
Blog
Vocabulary
Sign In
Sign Up
PMP Exam Simulator
Duration
3h 50m 0s
Questions
Start
Accelerate Mock Exam
Display correct answer
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Integration Management
An application change has been requested by the primary customer during user testing. What should you do as a project manager?
Make sure the scope change complies with all relevant contractual provisions.
Inform the project sponsor of changes to scope, cost and schedule.
Develop a risk mitigation plan.
Create a formal change request.
Next