The project you are managing is to construct a hotel with very unique exterior. A change request from the customer has been received. This change will delay the project for 7 days and will require additional $4000. The customer says that this change will considerably improve the project, and he doesn't mind the delay and extra money required. According to the policy of your company, you are supposed to get approval from the project office for any changes the can lead to delay of more than 3 days. What should be your course of action in this situation?