Integration Management
Which of the following statements is NOT true about the Project Management Information System (PMIS)?
PMIS can be electronic or manual.
PMIS defines how the project is executed, monitored and controlled, and closed.
PMIS is an automated system that can serve as a repository for information and a tool to assist with communication and with tracking documents and deliverables.
PMIS consists of the data sources and tools and techniques used to gather, integrate, analyze and disseminate the results of the combined outputs of the project management processes.