PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Integration Management
Your company has received a project to design and implement a new application that will connect to a database server. You have been assigned to manage this project. Management of your company has requested that you create a method to document technical direction on the project and to document any changes or enhancements to the technical attributes of the project deliverable. Which one of the following would satisfy this request?