Integration Management
Your organization doesn't have a centralized Change Control Board (CCB). You have been assigned a project to renovate the University campus. You created a CCB for your project and you want to follow a robust Integrated Change Control process. All of the following are primary goals for performing the Integrated Change Control process EXCEPT: