PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Integration Management
The engineering department of the company has uncovered a problem with the cost accounting system. They asked the systems department to analyze and fix the problem. You are a project manager working with the cost accounting program on another project. The management issued a change request to the change control board to add the new work to your project. Your current project has CPI (cost performance index) of 1.2 and SPI (schedule performance index) of 1.3, which indicates that there is enough room to add work without delaying your current project or going over budget. However, you don't think that the new work fits within the project charter for your current project. Finally, you came to conclusion that both works do not overlap and can be done concurrently. They would also require different skill sets. The best thing to do is: