PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Integration Management
You are managing a project to build a 6-lane interstate highway. There are 25 stakeholders and 5 sponsors and you know how essential it is to have a plan for making sure everyone knows what version of the scope, schedule and other components of the project management plan is the latest version. Which of the following plans should you use to specify how versioning information is tracked?