lock iconIntegration Management

A project is chartered to determine new ways to extent the product life of one of the company's medium-producing products. Mary is a project manager and she comes from the engineering department; the team members come from the product management and marketing departments. The project planning and project scope statement are completed when a stakeholder notifies that there is a better way to complete one of the packages. The stakeholder supplies a technical review letter from his department proving that the new way would be faster. Mary has had similar situations with this department before on other projects and she was expecting this to happen. What is the first thing for Mary to do?