PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
You have been assigned to a big software product development project. During project executing, many changes have been made. This includes changes requested by the customer, which considerably changed the functionality of the originally requested product. Two team members left the company for personal reasons and four were reassigned to new projects. However, all of these six team members have been replaced. As the project progressed, many of the identified risks have occurred and have been successfully mitigated. What should the project manager do?