Quality Management
A project manager realizes that the members of the team have differences of opinion in regards to interpretation of the requirements. A lot of rework is needed. The project manager is trying to make changes that would help meet the quality requirements and reduce future rework. His manager wants to help him and asks if he has created a histogram, because: