PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Risk Management
You are managing a residential construction project with the budget of $1.5 million. Until now everything has been going smooth and you are currently on schedule and according to the schedule the project will be completed in 5 months. Unfortunately, there has been a world outbreak of COVID-19, also known as coronavirus, and there are cases confirmed in the city where you work. The authorities declared a national emergency and are urging all nonessential workers to stay home or work remotely. Also, the state officials made announcement that in 7 days they will lock down the city and all businesses except groceries, pharmacies and hospital facilities will have to close until further notice. What would you do in this unprecedented situation?