Cost Management
A cost performance index (CPI) of 0.75 means:
The project is getting 75 cents out of every dollar invested.
At this time, we expect the total project to cost 75 percent more than planned.
The project is progressing at 75 percent of the rate planned.
When the project is completed, we will have spent 75 percent more than planned.