PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

The project manager is working on a project to develop a mobile application for an airline company. This morning he had a meeting with the sponsor to review the cost estimate. The sponsor was very unhappy with the higher cost and he requested to reduce the estimate by at least 8%. The sponsor is not too worried about the project duration estimate and he offered help with the schedule is needed. The best course of action for the project manager in this situation is: