Cost Management
Which statement is FALSE about TCPI?
TCPI calculates the performance that must be achieved to meet financial and schedule goals.
TCPI usually determines the status on the remaining work with respect to the remaining funds.
If the cumulative CPI falls below the baseline plan, all future work must be performed below the TCPI to achieve the planned BAC.
If the cumulative CPI falls below the baseline plan, all future work must be performed at the TCPI to achieve the planned BAC.