PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

The project manager has been assigned to the project which is estimated to last 10 months and cost $95,000. As of today, 40% of the project is completed and the actual cost is $35,000. What can you say about the CPI in this scenario?