This app works best with JavaScript enabled.
PRACTICE
Home
Blog
Vocabulary
Sign In
Sign Up
Home
Blog
Vocabulary
Sign In
Sign Up
PMP Exam Simulator
Duration
3h 50m 0s
Questions
Start
Accelerate Mock Exam
Display correct answer
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Cost Management
The project manager is in the middle of preparing the cost management plan for his project. Which statement is FALSE about the cost management plan?
The WBS provides a framework for the cost management plan and a control account (CA) in the WBS is used to monitor and control the project cost.
Activity cost estimates will be rounded to a prescribed precision (as $100, $1,000...).
Units of measurement such as hours, days, weeks or a lump sum amount will be used to estimate resources.
The primary concern is to determine the amount of resources to complete the project activities.
Next