Cost Management
In which situation the Earned Value Management (EVM) will not be very useful?
To develop the project cost baseline.
To measure a project's progress against the project scope, cost and schedule baselines.
To forecast future performance and the project's completion date and final cost.
To provide schedule and budget variances during the project.