lock iconCost Management

You are successfully overseeing a project with the budget of $950,000. According to the most recent earned value report, the CPI is 1.1, the SPI is 0.9 and PV is $650,000. You want to find out how much more the project will cost. What is the ETC (estimate to complete) for the project?